Developers Accountable for Tracking Sprint Progress in Scrum
Get 212 more PSM I practice questions
Complete explanations included
Question
Who is accountable for tracking the remaining work toward the Sprint Goal? (choose the best answer)
Answer
- D. The Developers.
Explanation
Expert Author
Sarah Chen
Certified Scrum Master & Agile Coach
Sprint ceremonies, team facilitation, impediment removal
Why Other Options Are Wrong
Real-World Application
Common Pitfalls
Students often confuse the roles and responsibilities of the Scrum Master and Product Owner with that of the Developers. They may mistakenly believe that tracking work is a shared responsibility rather than a specific accountability of the Developers.
Key Concepts
Scrum Guide Reference
Scrum Guide 2020 - Section 3.3: The Developers
Want More PSM I Practice Questions?
Get 212 additional questions with detailed explanations.
More PSM I Questions
Defining Done: Key Purposes of the Scrum Definition of Done
Developers select a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items done by the end of the Sprint. Which three phrases best describe the purpose of a Definition of Done?(choose the best three answers)
Scrum Master's Guide: Addressing Data Security Concerns
A Developer takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do? (choose the best answer)
Resolving Scrum Team Conflicts and Removing Disruptive Members
A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team? (choose the best answer)